Short answer
Open a space, select Reports, then More reports. Scrum spaces get ten reports (burndown, burnup, sprint report, velocity, control chart, cumulative flow, epic report, epic burndown, release burndown, version report). Kanban spaces get the control chart and cumulative flow diagram. Team-managed spaces get burnup and velocity. Every space also has eleven general reports for analysing work items, such as Created vs Resolved and Pie Chart. For anything else, save a JQL filter and put gadgets on a dashboard.
A note on words: Jira Cloud now calls projects spaces and issues work items. Older guides, Jira Data Center and many Marketplace apps still use project and issue. They mean the same thing. This guide uses the current Cloud names.
How to open a report in Jira Cloud
- Go to the space you want to report on.
- Select Reports in the space navigation. You land on the space insights dashboard.
- Select More reports to open the classic report catalogue.
- Pick the report.
Two things catch people out. First, a company-managed space can have several boards, and the classic reports run against the board you are looking at. Switch to the right board before you open a report. Second, the space insights dashboard uses data from the whole space and ignores the board filter, so its numbers can differ from the classic reports.
Reports for scrum spaces
These ten reports are available in company-managed spaces that use the scrum template.
| Report | Applies to | What it shows |
|---|---|---|
| Burndown Chart | Sprints | Work remaining in the sprint against an ideal line, so you can see whether the sprint goal is likely. |
| Burnup Chart | Sprints | Work completed against the sprint's total scope. Scope changes show as a moving top line. |
| Sprint Report | Sprints | Work completed or pushed back to the backlog in each sprint. Useful for spotting overcommitment. |
| Velocity Chart | Sprints | Work committed and completed per sprint, to estimate what the team can take on next. |
| Control Chart | Space, version or sprint | Cycle time per work item, to judge whether past performance predicts future delivery. |
| Cumulative Flow Diagram | Any period | How many work items sit in each status over time. Widening bands point at bottlenecks. |
| Epic Report | Epics | Progress towards completing one epic over time, including incomplete and unestimated work. |
| Epic Burndown | Epics | The projected number of sprints needed to finish an epic. |
| Release Burndown | Versions | The projected release date of a version, for teams that work in sprints. |
| Version Report | Versions | The projected release date of a version, based on the team's progress. |
Reports for kanban and team-managed spaces
Kanban spaces get two of the agile reports: the Control Chart for cycle time and the Cumulative Flow Diagram for work per status over time. For throughput per week, add a Created vs Resolved gadget to a dashboard (see dashboards).
Team-managed software spaces get the Burnup Chart and the Velocity Chart for sprints. They also get space insights.
General reports for analysing work items
These reports work on a whole space or on a saved filter, whatever template the space uses. The last four appear only when a Jira administrator has turned on time tracking.
| Report | What it shows | Shows people? |
|---|---|---|
| Average Age | Average age of unresolved work items. Tells you whether the backlog is being kept up to date. | No |
| Created vs Resolved | Created against resolved work items over time. Red areas mean the backlog grew, green means it shrank. | No |
| Pie Chart | Work items grouped by a field you choose, such as Status, Priority or Assignee. | Yes, by Assignee |
| Recently Created | Work items created per period and how many of them are already resolved. | No |
| Resolution Time | How long work items took to resolve, per period. | No |
| Single Level Group By | Results of a filter grouped by one field, with the status of each group. Shows up to 1,000 work items. | Yes, by Assignee |
| Time Since | Work items plotted against the date a field was set, such as Created, Updated or Resolved. | No |
| Time Tracking | Original estimate, remaining estimate and time spent for the work items in one version. | No |
| User Workload | Unresolved work items assigned to one person and their remaining estimate, per space. | Yes, one person |
| Version Workload | Outstanding work per person and per work item before a version is done. | Yes |
| Workload Pie Chart | Relative workload of each assignee for a space or filter. | Yes |
If Jira is connected to Confluence you can also build a Change Log and a Status Report on a Confluence page. Marketplace apps add Gantt charts, timesheets and SQL-style reporting.
Reading the Jira burndown chart
The burndown chart plots remaining work (vertical axis) against the days of the sprint (horizontal axis). The grey guideline runs straight from the sprint's starting scope to zero. The red line is what really happened.
- What it counts is the board's estimation statistic: story points, original time estimate, work item count or a numeric custom field. Change it in the board settings under Estimation.
- Done means the right-most column of the board, and To Do means the left-most. If the team forgets to move cards, the line stays flat even when work is finished.
- Sub-task estimates are not counted. Only the parent work items burn down.
- Flat stretches mean nothing reached Done, often because of blockers or because cards are moved in batches. Steps up mean scope was added or estimates went up after the sprint started.
- The burndown chart exists only for scrum boards in company-managed spaces.
Reading the Jira velocity chart
Each sprint gets two bars.
- Commitment (grey) is the total estimate of the sprint when it started. Work added later is not in this bar.
- Completed (green) is the estimate of the work that was done when the sprint closed, including work added after the start.
The chart shows the team's most recent completed sprints and an average of the last several, which is the number teams use to plan the next sprint. Like the burndown chart, it ignores sub-task estimates and uses the board's estimation statistic. Velocity is a planning number for one team. Comparing it between teams says little, because each team sizes its own story points.
The sprint report is the natural companion: it lists what was completed, what was not, and what was added after the sprint started, which explains most gaps between the two bars.
Jira dashboards and gadgets
A dashboard is a page of gadgets, each fed by a space or a saved filter. It is where most teams build the reports Jira does not ship.
Create a dashboard
- Select Dashboards in the sidebar, then Create dashboard.
- Give it a name and description, choose who can view and edit it, and select Save.
- Select Edit, then Add gadget, and add the gadgets you need.
- To share it later, open the dashboard, select More actions (the three dots), then Rename or share, and fill in Viewers and Editors.
A dashboard holds at most 20 gadgets, and Atlassian has said it will not raise the limit in Cloud. A gadget only shows data to viewers who can see the filter behind it, so share the filter with the same people as the dashboard.
Gadgets that are useful for reporting
| Gadget | Use it for |
|---|---|
| Two Dimensional Filter Statistics | A table of a filter's results with one field on each axis, such as Assignee against Status. |
| Pie Chart | A filter's results grouped by Status, Priority, Assignee or another field. |
| Work item Statistics | A filter's results broken down by one field, as a list with counts. |
| Created vs Resolved | Whether incoming work outpaces finished work, per day, week or month. |
| Average Time in Status | How many days work items spend in each status. Long waits in review show up here. |
| Resolution Time and Average Age | How fast work gets done, and how old the open work is. |
| Sprint Burndown and Sprint Health | The current sprint at a glance, next to the other gadgets. |
| Filter Results | The work items behind any of the charts, as a list. |
Custom reports in Jira with JQL
Every custom report in Jira starts with a JQL query. Write it in the work item search (switch to JQL), check the results, save it as a filter and share it. Then point a gadget at it, or export it.
Some queries that answer common reporting questions:
project = PLAT AND resolved >= -30d ORDER BY resolved DESC
project = PLAT AND created >= startOfMonth() AND type = Bug
project = PLAT AND statusCategory != Done AND updated <= -14d
assignee in membersOf("platform-team") AND resolved >= -7d
status CHANGED TO "Done" BY currentUser() DURING (startOfWeek(), now())
The first lists everything resolved in the last 30 days, the second this month's new bugs, the third open
work nobody has touched for two weeks, and the fourth what a team resolved this week. The last one uses the
CHANGED operator with BY, which finds work items a specific person moved to Done,
whoever is assigned now. CHANGED works only on Assignee, Fix Version, Priority, Reporter,
Resolution and Status. In Jira Cloud, BY takes an account ID or currentUser().
When a filter and gadgets are not enough
- CSV export. From the work item search, Export CSV supports up to 10,000 work items per export in Jira Cloud. Split larger sets into several filters, for example by month.
- REST API. The Jira Cloud REST API returns the same data as JQL, including the changelog of each work item, for scripts and BI tools.
- Atlassian Analytics and the Data Lake. Included in the Cloud Enterprise plan for Jira, Jira Service Management and Confluence. It queries Atlassian data across products with SQL and visual charts.
- Marketplace apps such as eazyBI and Custom Charts for Jira add pivot tables, time in status reports and more chart types.
How to see work per person in Jira
Managers ask this more than any other reporting question, and Jira answers it only in part. What works out of the box:
-
A Two Dimensional Filter Statistics gadget with Assignee on one axis and Status on the
other, fed by a filter such as
project = PLAT AND resolved >= -30d. This gives a table of resolved work per person for the last 30 days. - A Pie Chart grouped by Assignee, for the share of open work each person holds.
- The Workload Pie Chart, User Workload and Version Workload reports, if the team logs estimates and time.
- The
status CHANGED TO "Done" BYquery above, one person at a time.
What Jira does not show per person, however you configure it:
- Who did the work, as opposed to who holds it now. The reports count the current assignee. Work handed over at review time is credited to the last person.
- Comments, reviews and status changes per person as a count over time. The data is in each work item's history, but no report or gadget adds it up.
- One person across several spaces, unless you write a filter that spans all of them.
- Work outside Jira. A developer's pull requests and reviews live in GitHub, a writer's pages in Confluence, and everyone's messages in Slack or Microsoft Teams.
- A comparison with the rest of the team, such as the team median, without a spreadsheet.
This gap is why we are building Uptakely. It reads activity from Jira, Confluence, GitHub, Slack, Microsoft 365 and AI tools through their admin APIs and audit logs, and shows each person and team side by side: work items created and closed, status changes, cycle time, pages edited, pull requests merged, reviews given. Managers see their own teams by default. It is in development, and you can join the waitlist below. For which numbers to look at per role, see our guide on how to measure employee productivity.
Jira Cloud and Jira Data Center
The reports above exist in both, with older names in Data Center (issues and projects instead of work items and spaces). Atlassian is ending Data Center: sales to new customers stopped on 30 March 2026, existing customers can expand licences until 30 March 2028, and Data Center products and their Marketplace apps become read-only on 28 March 2029. If you are planning reports for the long run, plan them in Cloud.
Questions people ask about Jira reports
How do I run a report in Jira?
Open the space, select Reports, then More reports, and choose the report. In a company-managed space with several boards, switch to the right board first.
What reporting tools are available in Jira?
Agile reports, general work item reports, space insights, dashboards with gadgets, JQL filters with CSV export, the REST API, Atlassian Analytics on the Enterprise plan, and Marketplace apps.
Can Jira show a report per user?
Partly. Group by Assignee in a Pie Chart or Two Dimensional Filter Statistics gadget, or use the workload reports when time tracking is on. These count the current assignee and only cover Jira.
How do I create a custom report in Jira?
Save a JQL query as a filter, share it, and add gadgets that use it to a dashboard. Export to CSV or use the REST API for anything the gadgets cannot draw.
How many work items can I export from Jira Cloud?
Up to 10,000 per CSV export from the work item search.
Is Jira end of life?
Jira Cloud is not. Jira Data Center reaches end of life on 28 March 2029, along with Atlassian's other Data Center products.
See work per person across Jira, GitHub and Confluence
Uptakely is in development. Join the waitlist for early access and tell us which tools to connect first. We send one email when it is ready.
Sources
- Atlassian Support, Generate a report: support.atlassian.com/jira-software-cloud/docs/generate-a-report
- Atlassian Support, Dashboard gadgets: support.atlassian.com/jira-cloud-administration/docs/use-dashboard-gadgets
- Atlassian Support, View and understand the burndown chart and the velocity chart: burndown chart, velocity chart
- Atlassian Support, JQL operators: support.atlassian.com/jira-software-cloud/docs/jql-operators
- Atlassian Support, Export over 10,000 work items in Jira Cloud: support.atlassian.com/jira/kb/export-over-10-000-work-items-in-jira-cloud
- Atlassian, gadget limit request JRACLOUD-69218: jira.atlassian.com/browse/JRACLOUD-69218
- Atlassian, What is Atlassian Analytics: atlassian.com/platform/analytics/what-is-atlassian-analytics
- Atlassian, Data Center end of life: atlassian.com/licensing/data-center-end-of-life
Checked on 26 November 2026. Jira changes often; tell us if something here is out of date.